Lowest Bid for Vehicle Washing Tender Raised Under Suspicion, Free Offer Eliminated
A tender by the Central Procurement Agency (CPA) related to vehicle washing services for government institutions has been challenged at the Procurement Monitoring Body (PMB). Company AJANI & ADAMI...
A Central Procurement Agency (CPA) tender for vehicle washing services to meet government needs has been contested at the Procurement Monitoring Body (PMB).
Company AJANI & ADAMI SH.P.K. has submitted an official complaint to the PMB, opposing the CPA’s decision to eliminate its bid and recommend the contract to another economic operator.
What stands out in this procurement process is the discrepancy between the two bids.
According to documents submitted to the PMB, AJANI & ADAMI SH.P.K. had offered €17,810, while EDA CARS AUTOMOBILE L.L.C., the operator recommended for the contract, presented a bid valued at €21,047.90.
Thus, the eliminated company’s offer was €3,237.90 lower than that of the recommended operator, reports ORAinfo.
Why Was the Company Eliminated?
In its complaint, AJANI & ADAMI disputes the CPA’s reasoning for its exclusion from the competition, which is linked to the company’s tax documentation and agreements to settle debts with Kosovo Tax Administration (KTA).
According to the documents, the company had signed an agreement with KTA on May 8, 2026, and also held a tax clearance certificate dated July 1, 2026.
Meanwhile, another agreement with KTA was signed on October 19, 2026, and a new tax clearance certificate was issued on October 22.
The CPA, in letter B42 dated October 26, 2026, justified the elimination by referring to the new tax documentation and the agreement date.
However, the company argues that the documents should be reviewed as a whole and that the contracting authority should verify whether the first agreement was active and respected during the relevant period of this tender.
Company Seeks CPA Decision Annullment
In its complaint to the Procurement Monitoring Body, the company asserts that principles of economic efficiency, effectiveness, transparency, and equal treatment of economic operators were violated during this procurement process.
It requests that the PMB review the tender documentation, the elimination reasoning, and how the bids were evaluated.
Additionally, the company demands verification of whether the same eligibility criteria were applied to the operator recommended for the contract.
In support of its claims, AJANI & ADAMI SH.P.K. has cited several previous decisions by the PMB concerning tax documentation and debt settlement agreements.
What Does the Company Seek from the PMB?
In its final request, the company demands the annulment of the contracting authority’s decision and a return of the procurement process to reassessment, arguing that the existing documents should be reviewed in line with the tender dossier requirements and provisions of the Public Procurement Law.
Until the PMB’s review and decision, the company’s claims remain subject to the complaint procedure. There is still no final ruling from the monitoring body regarding the legality of the CPA’s decision. /ORAinfo/
Source of the news: orainfo.net
Note: This material has been adapted for informational purposes by the Portal Kosovo.Today.