When will the Tirana-Durrës-Rinas railway line be completed? Infrastructure Minister Enea Karakaçi responds

Kosova.Today ·

Invited on ‘Tonight’ with Mirela Milorin, Infrastructure and Energy Minister Enea Karakaçi was asked when the Tirana-Durrës-Rinas railway line would be finished and when citizens could travel by train to Durrës and...

Invited on ‘Tonight’ with Mirela Milorin, Infrastructure and Energy Minister Enea Karakaçi was asked when the Tirana-Durrës-Rinas railway line would be completed and when citizens could travel by train to Durrës and the airport.

The minister stated that track-laying works are in the final phase, with over 90% completed, while the construction of the eight stations along the Tirana-Durrës line has reached around 75%.

Karakaçi said that Albanian Railways had selected the operator responsible for electrification works, with the contract currently under final review by the European Bank for Reconstruction and Development (EBRD), which funds the project.

“This is a legitimate question, in fact, and a very real concern for every citizen who watches and wonders how a segment like this can remain unfinished over 33 kilometres. Undoubtedly, railway infrastructure projects are complex. For example, the Vorë-Hani i Hotit line involves around 330 million euros in investment. The Tirana-Durrës project is of similar value and must be understood as feasible with EU grants. When the Albanian government applied for a grant and one was approved by the EU, we had an incomplete project. In this way, in 2016, only the Tirana-Durrës track segment, ending at the airport, was approved. However, for the railway to function, stations are also needed. The stations were later included in a subsequent project, with funding approved three years ago. Why? Trains will operate on something, and in this case, electrification is necessary, as the trains will be electric. The electrification contract was approved by parliament in the summer of this year. If you ask me the simplest question of when the Tirana-Durrës railway will be operational, I would say that track-laying works are in the final phase, with over 90% of the work completed. The construction of the eight stations from Tirana to Durrës is about 75% finished. Meanwhile, Albanian Railways has already selected the operator for electrification, which is the final remaining process. The contract is awaiting final approval by the EBRD, as we have a foreign financing agreement, and the bank is conducting the final review of the contractor. Once the contract is signed, it will take 12 months from that moment,” Karakaçi stated.

Road Tirana-Durrës: Karakaçi says it will open in the first two months of 2027, extension will reach Dajlan Bridge

The post When will the Tirana-Durrës-Rinas railway line be completed? Infrastructure Minister Enea Karakaçi responds appeared first on Euronews Albania.


Source of the news: euronews.al
Note: This material has been processed for informational purposes by the Kosova.Today portal.

Read on the full page
Të ngjashme

Protesters gather outside the Prime Minister’s Office, police disperse them (VIDEO)

16.11.2026

Rama: Chay Bowes, a Russian propaganda clown sanctioned by the EU

16.11.2026

Rama Wins CER Prize in Brussels: Albania at Heart of European Tolerance

17.11.2026

Ferit Hoxha in Brussels: Mine Action Key to Ukraine’s Recovery

17.11.2026